Over the course of six months, ALE received 30 heavy lifts from ten ships at Salalah Port in the South of Oman.
The heaviest of these 30 items was a column weighing 471te with an offset centre of gravity. Due to weight and route restrictions a four-file, ten-axle SPMT with bolsters was required to move the 60-metre long, 9-metre diameter vessel.