Subsea manifold removal project, UK

Overview

ALE has successfully loaded-in three redundant subsea manifolds for reclaiming in the Shetland Islands, UK.

 

Services Required

The subsea manifold units weighed 360t, 437t and 547t. ALE utilised different configurations of SPMTs to load-in the manifold units.

ALE needed to turn two of the units 90º on the barge prior to load-in.  As quay strength was a concern, ALE supplied additional quayside matting.

All three structures were successfully loaded-in over two days.