Transportation of three hopper vessel units, Malaysia

Overview

ALE has completed the transportation of three hopper vessel units, weighing between186t-348.2t, as part of the RAPID Project in Pengerang, Malaysia.

 

Services Required

ALE received the units at Tanjung Setapa Port and transported the heavylift cargo 8km to the project site using 36 axle lines of SPMT in a configuration of 2 x 2 file 18. ALE negotiated five 90° turns during the move. The convoy had to travel at a 90° angle so the hopper vessel could be positioned onto its erection area.

The hoppers traveled a total distance of 15km and ALE completed the transportation to the final location within 2.5 hours.