Transportation of three hopper vessel units, Malaysia

Overview

ALE has completed the transportation of three hopper vessel units, weighing between186t-348.2t, as part of the RAPID Project in Pengerang, Malaysia.

 

Services Required

ALE received the units at Tanjung Setapa Port and transported the heavylift cargo 8km to the project site using 36 axle lines of SPMT in a configuration of 2 x 2 file 18. ALE negotiated five 90° turns during the move. The convoy had to travel at a 90° angle so the hopper vessel could be positioned onto its erection area.

The hoppers traveled a total distance of 15km and ALE completed the transportation to the final location within 2.5 hours.

ALE Heavylift, Smarter, Safer, Stronger, ale, ALE, abnormal load engineering, heavy crane lifting, heavy transportation

  • Transportation of three hopper vessel units, Malaysia

Related Case Studies

© 2017 ALE | Acceptable Use Policy | Cookie Policy | Privacy Policy | Terms Of Website Policy | Anti Modern Day Slavery Statement | ALE Terms & Conditions