ALE completes 20,000t load-outs in South Korea

« Back to news

Overview

ALE has loaded-out two modules weighing a combined weight of over 20,000t for the Martin Linge platform project in South Korea.

The global heavylifting provider was contracted to perform both the weighing and load-out operations for the utility and process modules of the platform.

ALE’s specialist division, ALE-Offshore Services, executed the weighings using ALE’s centrally-controlled synchronised weighing system and weightors. The utility module weighed in at 9,580t and the process module weighed 10,850t.

The modules were then loaded-out onto the same vessel over two months. The load-outs took place in two separate operations using a specialised skidding system.

Read the full story here.

Read the case study here.