Your Javascript is switched off and this website requires Javascript to function correctly, therefore you are viewing a version with reduced functionality.

Case Studies

Sector:

Service:

Equipment:

Location:


Case Studies

Showing 733 Case Studies

Case Study

^

SECTOR: Oil and Gas   KEY BENEFITS: Global equipment fleet Swift mobilisation Reduced costs   PROJECT: Drawing on its global fleet of specialist transport equipment, ALE completed the efficient transportation of 22 engines for the Sangachal -2 Power Plant Project in Baku, Azerbaijan. ALE’s scope consisted of the 25km transportation of the engines, weighing 300t […]

mining module being transported on spmt

Case Study

^

SECTOR: Minerals and metals   KEY BENEFITS: Record-breaking transportation Challenging route Bespoke solution Minimised disruption   PROJECT: Challenged with the heavy haulage transportation of fifteen mining modules, including the largest and heaviest items ever transported in Guinea, ALE needed to design a bespoke solution to overcome the route’s various obstacles. ALE collaborated with Bolloré Logistics, […]

Mega Jack 300 shows its versatile efficiency when lifting a module

Case Study

^

SECTOR: Ports   KEY BENEFITS: Cost-effective Quick operations Increased stability Limited site space Bespoke solution   PROJECT: As part of providing the full onshore heavylifting solution for one of the largest refineries in the Middle East, ALE used its Mega Jack 300 for jacking-up 188 modules, measuring as large as 50m in length and weighing […]

alternative lifting of an amphitheatre using strand jacks

Case Study

^

SECTOR: Civil   KEY BENEFITS: Innovation Optimised space Co-ordination with third parties   PROJECT: ALE’s ability to provide innovative and specially-tailored heavylifting solutions enabled them to provide an alternative lifting solution to raise a roof section, weighing 400t (441 US t), for an amphitheatre in Milwaukee, USA. There was minimal space available at the site, […]

specialist transport with WW2 rescue vessel on SPT

Case Study

^

SECTOR: Shipyards   KEY BENEFITS: Bespoke solution Cost-efficient Minimised disruption   PROJECT: The design of bespoke equipment enabled ALE to complete the jacking, transportation and installation of a fragile Second World War rescue vessel. The specially-tailored solution minimised disruption and was the most cost-efficient method to install the vessel, measuring 34m long and weighing 92t, […]

Abkatun floatover

Case Study

^

Sector Offshore Key Benefits: Quick operations Innovation Reduced costs Bespoke engineering Reduced risk Project: ALE has delivered an integrated solution to help complete a phase of a major offshore project in Mexico. The global heavylifting contractors were tasked to perform weighing, jacking, load-out of the jacket and the platform. The first stage of the three-phased […]

final offshore wind farm transition piece being loaded

Case Study

^

SECTOR: Renewables – Wind   KEY BENEFITS: Innovative equipment Branch collaboration Cost-efficient   PROJECT: ALE’s offshore engineering expertise enabled them to complete the marine transportation, sea-fastening, load-out and ballasting of over 100 transition pieces (TPs) for one of the biggest offshore wind farms in the world, Ørsted’s Hornsea Project One. As well as drawing on […]

uk gantry crane move for HS2

Case Study

^

Sector: Civil Key benefits: Bespoke solution In-house expertise Quick mobilisation Reduced risk Minimised impact         Project: ALE has used its internal engineering expertise to create a special solution that could move a gantry crane over live rail lines in the safest way possible. ALE was tasked by the Costain Skanska joint venture […]

load test

Case Study

^

Sector: Civil Key benefits: Bespoke methodology In-house engineering Time saving Cost reductions       Project: ALE has used its in-house expertise to perform a bespoke load application, the first load test of its kind in Europe when conducting the weighing of a test pile in central London, UK. At 5,121t, it was also the […]

Case Study

^

SECTOR: Civil   KEY BENEFITS: Close coordination Swift installation Bespoke equipment   PROJECT: ALE has drawn on its experience in delivering tightly planned, efficient heavy lifting projects to complete the lifting of a cold box, weighing 272t (300 US t), in North Carolina, USA. The cold box measured 45.7m x 9.1m x 6.1m (150ft x […]

(Page 1 of 73) Next Page »

© 2019 ALE | Acceptable Use Policy | Cookie Policy | Privacy Policy | Gender Pay Gap Report | Anti-modern Day Slavery Statement | Terms Of Website Policy | ALE Terms & Conditions