Edvard Grieg EPC Project – LQ Load-out, Norway

Overview

ALE has successfully undertaken both the load-out and load-in of a 1260t living quarters module, Norway.

 

Services Required

This involved using sixty SPMT axles to locally site move and load-out the module onto the UR97 barge, this process was then reversed for the subsequent load-in.

ALE undertook the engineering for the ballasting and SPMTs, the site set-up, the ballast pump system and the winch systems.  Working with the client teams, ALE was also involved in the HAZOP and SJA processes.