Load-out of QPS Topsides and Jackets, Indonesia

ALE successfully completed the weighing, jacking and load-out of two Jackets and a topside.Quarter Platform South (QPS) included a 1,200te upper deck for a 158 person living quarters, gallery, recreational room, office, heli-deck and workshop. The 1,500te lower deck is for emergency diesel and fresh water storage and sewage treatment. The total weight was approximately 4,000te
including load-out support frames and beams. A total of 176 axles of SPMT were utilised, including 18 pumps for ballasting and 16 x 12 metre dragline boards as spreaders. The structure had to be jacked-up to one metre in order to be able to insert the SPMT’s and spreaders due to its low height during the fabrication stage. A total of 16 x 600te weighing jacks were used for the jack-up operation.
Share Button

  • Load-out of QPS Topsides and Jackets, Indonesia

© 2019 ALE | Acceptable Use Policy | Cookie Policy | Privacy Policy | Gender Pay Gap Report | Anti-modern Day Slavery Statement | Terms Of Website Policy | ALE Terms & Conditions