Mexilhao Project, Brazil

ALE was contracted to perform three skidding load-outs for a shipyard in Brazil.

The Load-outs were performed in two separate yards in the same basin in Rio. All three had to take place within 45 days and with a pull length of 250 metres. Using strand jacks, we successfully loaded out a 14,000te jacket and two topsides of around 7,500te and 8,000te, respectively.