Transportation of seven switch rooms, Malaysia

Overview

ALE has transported seven switch rooms, weighing 167.64t each, as part of the RAPID project in Pengerang, Malaysia.

 

Services Required

The switch rooms were loaded-in at Tanjung Setapa Port, then transported 8km to the project site using 36 axle lines of SPMT in a configuration of 2 x 2 file 18. During the move, ALE had to negotiate five 90° turns and travel at a 90° angle to position the switch room onto its foundation plinth.

ALE travelled a total distance of 15km, completing the transportation of each switch room in 2.5 hours. The entire RAPID project was completed over four months.

Share Button

  • Transportation of seven switch rooms, Malaysia