Reception and storage of refinery equipment, Venezuela

Overview

ALE has successfully received and transported 12 pieces of refinery equipment for the Puerto La Cruz Refinery’s, Deep Conversion Project.

 

Services Required

The 12 pieces of equipment ranged in size and weight, with some pieces as heavy as 143.9t and measuring up to 39.31m long, 6.54m wide and 7.41m high. The combined total weight came to 960t.

 

ALE received the refinery equipment from the MV Kraszewski Vessel using two transport configurations. The equipment was received on 20 axle lines of SPMT in 2 x 10 axles with 4 spacers. The equipment was transported 500m from the vessel and stored at the Port of Guanta. Here, it was taken into storage and prepared for onward transported to the refinery.

 

 

Recepción y almacenamiento de doce equipos,  Venezuela

 

Resumen

ALE ha realizado con éxito la recepción de 12 equipos para el Proyecto Conversión Profunda de la Refinería de Puerto La Cruz.

 

Servicios Requeridos

Los 12 equipos variaban en peso y tamaño, con dimensiones tope de 39,31m de longitud, 6,54m de ancho y 7,41m de alto y un peso máximo de 143,9t. El peso total combinado llegó a 960t.

 

ALE recibió el equipo de la refinería de escargado del barco MV Kraszewski Vessel. Dos configuraciones de transporte 2 x 10 SPMT + mesa separadora (4 líneas) fueron utilizadas durante esta actividad. Los equipos fueron transportados a 500m  y almacenados en el Puerto de Guanta para luego ser trasladados a la refinería.