Launching of San Pablo Bridge, Panama

 

Overview

ALE has successfully launched a steel bridge over San Pablo River in the city of Santiago de Veraguas, Panamá.

 

Services Required

 

The steel bridge weighed 800t. The bridge comprised of three spans, of 30m, 60m and 30m respectively. It was launched by using ten 90t skid shoes, two SLS700 strand jacks mounted on the abutment and eight 300t swivel plates mounted on the piles.

 

ALE concluded the manoeuvre by jacking the bridge deck, pile by pile. After launching the central 60m span, the next pile was reached with a deflection over 500mm. This was completely recovered only by the shape of the launching nose.

 

ALE completed the bridge launch in three days, working nine hours each day.

 

 

Lanzamiento de puente San Pablo, Panamá

 

Resumen

ALE ha realizado exitosamente el lanzamiento de un puente metálico sobre el Río San Pablo en la ciudad Santiago de Veraguas, Panamá.

 

Servicios Requeridos

El peso total del puente fue de 800t, se lanzó desde un solo estribo utilizando skidshoes de 90t, unidades de tiro SLS700 y chapones de deslizamiento de 300t.

 

Finalmente se realizó el gateo final pila a pila. Se trata de un puente de 3 vanos, de 30m, 60m y 30m respectivamente. Luego del lanzamiento del vano central de 60m se arribó a la siguiente pila con una flecha mayor a 500mm, recuperada íntegramente con la geometría en pendiente de la nariz de lanzamiento

 

Para completar el lanzamiento se requirieron tres jornadas de nueve horas de operación.

 