ALE has successfully completed the transportation and load-out of one Bluewater lower turret for the KAOMBO South FPSO project.

 

Services Required

The turret consisted of two pieces, the upper weighing 1,400t, and the lower weighing 1,950t.

ALE transported the two pieces from the fabrication location to the quayside using 88 axle lines of SPMT.

The pieces were then loaded-out onto a self-propelled vessel supplied by the client. ALE then offloaded the pieces on-board the vessel onto the client’s grillage.