Installation of wind turbine generators, Thailand

Overview

ALE has performed an installation, including cranes and the mechanical and electrical installation (M&E) package, of 12 wind turbine generators for Power China Hua Dong at Lam Takhong wind farm, in Nakhon Ratchasima Province, Thailand.

 

Services Required

ALE utilised a CC2800 crawler crane to install the wind turbine generators which have a hub height of 94m.

ALE utilised their specialist Wind Services division to execute the mechanical and electrical installation.

Whilst performing the installation of the 2.0MW wind turbine generators, ALE had to negotiate the steep terrain onsite during the relocation of the CC2800.