Array ( [0] => WP_Term Object ( [term_id] => 58 [name] => Barges [slug] => barges [term_group] => 0 [term_taxonomy_id] => 60 [taxonomy] => equipment [description] => [parent] => 0 [count] => 29 [filter] => raw )[1] => WP_Term Object ( [term_id] => 48 [name] => Barging [slug] => barges [term_group] => 0 [term_taxonomy_id] => 50 [taxonomy] => services [description] => [parent] => 0 [count] => 22 [filter] => raw )[2] => WP_Term Object ( [term_id] => 36 [name] => Load-in & Load-out [slug] => load-in-load-out [term_group] => 0 [term_taxonomy_id] => 38 [taxonomy] => services [description] => [parent] => 0 [count] => 78 [filter] => raw )[3] => WP_Term Object ( [term_id] => 16 [name] => Ports [slug] => ports [term_group] => 0 [term_taxonomy_id] => 18 [taxonomy] => sectors [description] => [parent] => 0 [count] => 45 [filter] => raw )[4] => WP_Term Object ( [term_id] => 104 [name] => South East Asia [slug] => south-east-asia [term_group] => 0 [term_taxonomy_id] => 106 [taxonomy] => location [description] => [parent] => 0 [count] => 53 [filter] => raw )[5] => WP_Term Object ( [term_id] => 70 [name] => Transportation [slug] => transportation [term_group] => 0 [term_taxonomy_id] => 72 [taxonomy] => equipment [description] => [parent] => 0 [count] => 278 [filter] => raw ))

Transportation, load-out and load-in of RTGs, Thailand

Overview

ALE has performed the load-out and load-in of three rubber tyred gantry (RTG) cranes, each weighing 120t, in Thailand.

Services Required

ALE transported the RTGs to Suksawat Port using 24 axle lines of SPMT in a configuration of 2 x 4 file 6 axle lines. Additionally, SPMT spacers were used to reduce the total number of axle lines needed.

The RTGs were loaded-out onto a barge, where they were sea fastened. The RTGs were then transported by barge to Kerry Port. ALE completed the load-in at Kerry Port and transported the RTGs approximately 3.5km to the final container terminal.

ALE faced the challenge of transporting the RTGs on a route with limited space. Furthermore, the RTGs’ high centre of gravity made them unstable and ALE needed to find the best solution to stabilise the load. Both the load-out and the load-in were completed in one-day operations.