Array ( [0] => WP_Term Object ( [term_id] => 96 [name] => Europe [slug] => europe [term_group] => 0 [term_taxonomy_id] => 98 [taxonomy] => location [description] => [parent] => 0 [count] => 185 [filter] => raw )[1] => WP_Term Object ( [term_id] => 22 [name] => Shipyards [slug] => shipyards [term_group] => 0 [term_taxonomy_id] => 24 [taxonomy] => sectors [description] => [parent] => 0 [count] => 37 [filter] => raw )[2] => WP_Term Object ( [term_id] => 30 [name] => Skidding [slug] => skidding [term_group] => 0 [term_taxonomy_id] => 32 [taxonomy] => services [description] => [parent] => 0 [count] => 44 [filter] => raw )[3] => WP_Term Object ( [term_id] => 68 [name] => Skidding Systems [slug] => skidding-systems [term_group] => 0 [term_taxonomy_id] => 70 [taxonomy] => equipment [description] => [parent] => 0 [count] => 50 [filter] => raw ))

Versatile skidding equipment enables challenging engine exchange, Spain

Sector:

Shipyards

Key Benefits:

Quick mobilisation

Minimised disruption

Bespoke solution

Versatile equipment fleet

Project:

A complex engine exchange onboard a cargo ship at Navantina Shipyard in Ferrol, Spain, called for a tailored solution at short notice. ALE’s versatile skidding equipment enabled them to replace the old engine with a new one, both weighing 67t, with minimal disruption.

Before any work could begin, an incision had to be made in the side of the vessel, through which the exchange could be performed.

For the extraction of the old engine, ALE first removed the alternator, weighing 36t. It was skidding along the top of a turning table, which was supported on 25t capacity skid beams, to a temporary landing area inside the engine room. The operation had to take place in a narrow area so to obtain additional space for the removal of the engine, the engine block was skidded transversally.

The motor was then raised using chains that had been installed in the upper cover. This enabled two turning tables to be installed, which were used to rotate the engine by 90º. The motor was skidded to be aligned with the skid tracks coming off the vessel.

As the ship was afloat, ALE needed to account for the effect of the tidal variations when moving the engine from the ship to the dock. Jumping beams were supported on hydraulic jacks, which enabled a constant level to be maintained for the installation of skid tracks. The old engine could then be smoothly skidded onto the dock. The installation of the new engine was completed following the above sequence in reverse.

The versatility of ALE’s skidding equipment, their resourcefulness, and the experience of the engineering team enabled ALE to mobilise at short notice, completing these challenging manoeuvres in a narrow space while overcoming numerous obstacles.

Equipos de deslizamiento versátiles permiten el complejo cambio de un motor en un espacio reducido, España

SECTOR:

Astilleros

BENEFICIOS CLAVE:

Movilización rápida

Interrupción minimizada

Soluciones a medida

Flota de equipos versátiles

PROYECTO:

Complejo reemplazo de motor a bordo de un buque de carga en el Astillero de Navantia en Ferrol, España, ha exigido una solución personalizada. La versatilidad del equipo de deslizamiento de ALE permitió reemplazar con mínimas alteraciones un motor viejo por uno nuevo, ambos con un peso de 67t. En primer lugar, se realizó una cesárea en el costado del buque, a través de la cual se realizaría el reemplazo del motor.

Para la extracción del motor antiguo, ALE retiró primero el alternador, con un peso de 36t, deslizándolo encima de una mesa de giro apoyada sobre patines de deslizamiento de 25t de capacidad hasta una zona de apeo temporal dentro de la sala de máquinas. Debido a que la operación tuvo que realizarse en un área angosta, para obtener espacio adicional para maniobra, el bloque motor se deslizó transversalmente. Posteriormente, el motor se elevó utilizando diferenciales de cadenas que se habían instalado en la cubierta superior y se realizó una rotación de 90º del motor usando 2 mesas giro. Lo que permitía su alineación con las pistas de deslizamiento que salían del barco.

Ya que el barco estaba a flote, ALE tuvo que tener en cuenta el efecto de las variaciones de las mareas al mover el motor desde el barco al muelle. Para ello utilizó unas vigas de salto apoyadas sobre gatos hidráulicos que absorbían las posibles variaciones de la marea, permitiendo mantener las vigas a nivel con la cota de deslizamiento instalada en el barco. Pudiendo así deslizar fácilmente el viejo motor al muelle. La instalación del nuevo motor se completó siguiendo la secuencia anterior en orden inverso.

La versatilidad de los equipos de deslizamiento de ALE, su versatilidad y la experiencia del equipo de ingeniería, permitieron a ALE movilizarse con poca antelación, completando estas complejas maniobras en un espacio angosto y con numerosas interferencias.